I feel better about timing because as part of the contract he has to have it all finished by Jan 1st or he starts paying me $125/week for each week over.
Almost finished
Saturday, September 1, 2018
Garage framing Commences
So the garage floor was poured in May, it sat for 2 months and Al finally got around to the framing. He started that this last week. After framing, the specialized roofing (TPO) with the solar panel studs will start. This is a unique one of one garage plan, w an angled roof, so very non-standard. They had made SOME more progress yesterday, but had to rip it out because it was not according to plans. But not my issue. I'm not paying for his misstep. And he knows that. Everyday after they leave which is about 3:45pm, I go around and pick up all the nails, left over trash, although they make a small effort to cleanup, and use an electric blower to get rid of all the sawdust and dirt. It's a clean work site.